PUBLISHED December 27, 2021

Welcome to 900 Randolph, a new mid rise were working on in the west loop

Were finishing up grade beam excavation and fine grading stone for slab on grade

Also, completing site utility work with the water main install

We work in very tight quarters all of the time, which requires a ton of communication

And coordination with other trades